Guide / Air & equipment

Potential to emit versus actual emissions

Actual emissions describe what happened during a stated period. Potential to emit (PTE) asks how much the source could emit under its physical and operational design, considering only limits that qualify under the applicable program. A quiet year changes the first number, not necessarily the second.

Open guide
Guide / Air & equipment

Convert pounds per hour to short tons per year

Multiply an emission rate in pounds per hour by operating hours per year, then divide by 2,000 pounds per US short ton. The conversion is simple; choosing a rate and time period that belong together is the important part.

Open guide
Guide / Air & equipment

Choose an emission factor that fits the process

An emission factor relates pollutant mass to an activity such as heat input or material processed. EPA notes that AP-42 factors generally describe averages across sources, not guaranteed maximums, permit limits, or proof of compliance.

Open guide
Guide / Air & equipment

When can an hours limit change a PTE estimate?

A production forecast, staffing plan, or verbal promise is not an enforceable operating restriction. Under Part 70, a restriction counted as part of design must meet the definition in § 70.2. Practical enforceability also depends on whether compliance can be determined from the terms and records.

Open guide
Guide / Air & equipment

Aggregate hazardous air pollutants without double counting

Track each listed hazardous air pollutant (HAP) across independent releases, then combine nonoverlapping HAP totals. Under the usual federal section 112 major-source definition, 10 short tons/yr of one HAP and 25 short tons/yr combined are separate, inclusive screens: either can matter. Neither is an exemption test.

Open guide
Guide / Air & equipment

Air construction permit vs. operating permit: adding equipment

A construction permit answers “what may we build or change?” It can also set limits that last through operation. A Title V operating permit brings the site’s applicable requirements together and spells out how the operator demonstrates compliance. Having one does not authorize a project under the other; not every facility needs Title V.

Open guide
Guide / Air & equipment

What data should an emergency generator file contain?

The “standby” label on a generator describes a product, not necessarily its regulatory use. A reviewer needs the engine configuration, dates, location, applicable source category and actual dispatch purposes to evaluate stationary engine requirements.

Open guide
Guide / Air & equipment

Evaluate a coating or solvent substitution

A lower VOC label does not establish a lower HAP rate or compliance with the existing permit. Compare the old and new systems as applied, including thinning, hardeners and cleanup, on the same production basis.

Open guide
Guide / Air & equipment

Exemption, permit by rule, or individual permit?

These routes depend on the jurisdiction and its approved program. An exemption can relieve a specified permitting obligation under stated conditions. A permit by rule can authorize a defined class subject to its terms; it is not a universal self-approval. An individual permit sets project-specific conditions through agency review.

Open guide