How to approach it
- Find the effective instrument and quote the condition, unit IDs, covered operating modes, hours cap, and averaging period. A calendar-year limit is not interchangeable with a rolling 12-month limit.
- Check the meter or log specified by the condition, how readings are reconciled, and how shared caps work. Identify who calculates the total and how missing readings are handled.
- Show both the unrestricted calculation and the condition-based alternative. A proposed cap stays a scenario until effective and accepted for the relevant program.
Worked example
A hypothetical condition caps two pumps together at 2,000 pump-hours per rolling 12 months. At equal emission rates of 1.8 lb/h, the cap corresponds to 1.8 short tons/yr combined, not 1.8 tons for each. One hour with both running uses two pump-hours under that wording.
Next step
Have the reviewing authority confirm how the condition counts concurrent operation before using it to limit source-wide PTE.