When can an hours limit change a PTE estimate?

A production forecast, staffing plan, or verbal promise is not an enforceable operating restriction. Under Part 70, a restriction counted as part of design must meet the definition in § 70.2. Practical enforceability also depends on whether compliance can be determined from the terms and records.

How to approach it

  1. Find the effective instrument and quote the condition, unit IDs, covered operating modes, hours cap, and averaging period. A calendar-year limit is not interchangeable with a rolling 12-month limit.
  2. Check the meter or log specified by the condition, how readings are reconciled, and how shared caps work. Identify who calculates the total and how missing readings are handled.
  3. Show both the unrestricted calculation and the condition-based alternative. A proposed cap stays a scenario until effective and accepted for the relevant program.

Worked example

A hypothetical condition caps two pumps together at 2,000 pump-hours per rolling 12 months. At equal emission rates of 1.8 lb/h, the cap corresponds to 1.8 short tons/yr combined, not 1.8 tons for each. One hour with both running uses two pump-hours under that wording.

Next step

Have the reviewing authority confirm how the condition counts concurrent operation before using it to limit source-wide PTE.