How to approach it
- Photograph the engine and generator nameplates. Distinguish mechanical brake horsepower from electrical kW; obtain the engine family, model year, build and installation dates, fuel, ignition type and certification documents.
- Separate outage response, maintenance/testing and any other dispatch. Save dispatch requests, dates, start/end meter readings and reasons; check applicable meter and record requirements. Do not assume a testing allowance covers paid dispatch or all non-emergency use.
- Check applicable provisions of Part 63 Subpart ZZZZ and Part 60 engine standards, local construction rules, and existing permit terms. Match emission rates to the actual engine and load, not a similarly sized generator.
Worked example
A log shows 7.5 h during a utility outage, 4 h of scheduled tests and 2 h shaving peak demand. The meter change is 13.5 h, but presenting it all as “emergency hours” would conceal a use the reviewer must assess separately.
Next step
Send the nameplate photos, engine spec sheet and purpose-coded hour log together; flag proposed dispatch arrangements before agreeing to them.