How to approach it
- Read the numerator and denominator on the source sheet. A lb/h rate can be annualized directly; lb/MMBtu needs heat input in MMBtu/h first. A short ton is not a metric tonne.
- Choose hours for the question: meter records for actuals, or maximum operating hours supported by the design and qualifying restrictions for a potential scenario.
- For a changing rate, multiply each operating mode by its own hours before summing. Verify the modes do not overlap and retain unrounded values until the total.
Worked example
A dryer ran 300 h at 4 lb/h and 900 h at 1 lb/h. Its estimate is (1,200 + 900) ÷ 2,000 = 1.05 short tons for the period. Using the 4 lb/h rate for every hour instead would answer a different question.
Next step
Record the rate source and hours source next to each multiplication so a reviewer can reproduce it.