How to approach it
- Before installation: identify the new unit, connected equipment and any overlap with a retiring unit. Give the air agency the process diagram, maximum rates by pollutant and first planned construction activity.
- Ask which construction approval or documented exemption applies, and which work must wait. Read any issued approval for requirements at startup—such as a notice, a control check or a test deadline—not just permission to install.
- For the operating file, mark the pages affected: equipment table, emission limits and monitoring terms. Ask the issuing agency whether and when a notice, amendment or modification is required. If the site has no Title V permit, ask whether the changed source now needs one or a state operating permit.
Worked example
An additional dryer shares a stack with the original dryer. The stack ID has not changed, but the project may increase heat input and two dryers could run together. A reviewer needs the combined capacity and permit wording, not just the unchanged equipment list.
Next step
Ask the authority which steps must occur before construction, startup and operation; put each response on the project schedule.