Air construction permit vs. operating permit: adding equipment

A construction permit answers “what may we build or change?” It can also set limits that last through operation. A Title V operating permit brings the site’s applicable requirements together and spells out how the operator demonstrates compliance. Having one does not authorize a project under the other; not every facility needs Title V.

Can installation start under the existing operating permit?

Do not use the operating permit alone to release installation. Ask the air authority about preconstruction review for the proposed change, then determine whether the operating permit also needs a revision.

EPA — New Source Review: major and minor construction permits

How to approach it

  1. Before installation: identify the new unit, connected equipment and any overlap with a retiring unit. Give the air agency the process diagram, maximum rates by pollutant and first planned construction activity.
  2. Ask which construction approval or documented exemption applies, and which work must wait. Read any issued approval for requirements at startup—such as a notice, a control check or a test deadline—not just permission to install.
  3. For the operating file, mark the pages affected: equipment table, emission limits and monitoring terms. Ask the issuing agency whether and when a notice, amendment or modification is required. If the site has no Title V permit, ask whether the changed source now needs one or a state operating permit.

Worked example

An additional dryer shares a stack with the original dryer. The stack ID has not changed, but the project may increase heat input and two dryers could run together. A reviewer needs the combined capacity and permit wording, not just the unchanged equipment list.

Next step

Ask the authority which steps must occur before construction, startup and operation; put each response on the project schedule.