The inspection found no asbestos. Is demolition notice still required?

Yes, for an ordinary demolition of a facility covered by the federal rule. A no-asbestos finding changes which provisions apply; it does not cancel the demolition notice.

Open guide
Guide / Demolition notices

Is partial demolition a renovation?

Not necessarily. Under the federal definitions, wrecking or taking out any load-supporting structural member is demolition, even if most of the building stays. Alterations without that structural change generally fall under renovation. Intentional burning of a facility also counts as demolition.

Open guide
Guide / Demolition notices

Do small quantities mean an inspection is unnecessary?

No. For an affected facility under § 61.145(a), the thorough inspection comes before the applicability decision. The renovation quantity test concerns regulated asbestos-containing material (RACM) expected to be disturbed, not a guess about the whole building.

Open guide
Guide / Demolition notices

Which materials go in the linear, area and volume boxes?

Use linear feet for pipe material and square feet for other facility components. Cubic feet apply only to material off facility components when its length or area could not previously be measured. A container’s capacity is not a substitute for available original measurements.

Open guide
Guide / Demolition notices

Does the small-residential exclusion cover this project?

The federal facility definition excludes residential buildings with four or fewer dwelling units, but a unit count alone does not settle coverage. An installation, former regulated use, or larger redevelopment can change the result. State and local rules may cover a home the federal rule excludes.

Open guide
Guide / Demolition notices

Which weekdays and holidays count?

For the federal asbestos rule, working days are Monday through Friday, including holidays on those days. Do not assume the state’s clock matches: MassDEP’s AQ 06 instructions, for example, exclude holidays.

Open guide
Guide / Demolition notices

What if the start moves earlier or later?

For work covered by § 61.145(b)(3)(iv), a delay and an acceleration follow different rules. Do not just edit the crew calendar. Work must not begin on a date other than the one in the written updated notice.

Open guide
Guide / Demolition notices

When is an ordered demolition or emergency renovation different?

A qualifying ordered demolition requires a state or local government order based on structural unsoundness and danger of imminent collapse. Emergency renovation is a separate category for a sudden, unexpected event requiring immediate action for specified safety, equipment or financial reasons. Neither is a general waiver.

Open guide
Guide / Demolition notices

What should the owner get back from the filer?

Ask for a record that connects the inspected scope, the notice actually sent, its delivery, and the dates the team is using. Hiring a filer does not make an owner or operator’s obligations disappear.

Open guide