How to approach it
- Confirm that the inspection covered the whole demolition footprint, including later changes to the plans.
- Use the demolition notice for the site address. Under § 61.145(a)(2), the notice still identifies the owner/operator, building size, floors, age, uses, inspection method, quantities and demolition dates. Record what the inspector found; an inaccessible space is not a negative finding.
- Describe what the team will do if unexpected regulated material is found. Keep the inspection, filed notice and proof of delivery together; a building permit is not proof of air-agency filing.
Worked example
A warehouse inspection covers the full building and reports no asbestos. The owner uses the below-threshold/no-asbestos demolition notice route under § 61.145(a)(2), measured back from demolition.
Next step
Find the receiving agency and its demolition form.