How to approach it
- For a delay, call the agency as soon as possible before the original start; provide the written new date as soon as possible before and no later than the original start.
- For an earlier start, provide written notice at least ten federal working days before the new start of the covered activity. Check local filing rules too.
- Link the update to the original notice. Review other changes as well: the federal rule calls for updating as necessary, including when the affected asbestos amount changes by at least 20 percent.
Worked example
A demolition originally noticed for April 12 moves to April 19. The filer calls before April 12, submits the written revision no later than April 12, and gives the owner the revised date and filing record.
Next step
Reconcile the owner’s, contractor’s and agency’s copies of the schedule.