How to approach it
- Identify the applicable notice category and first relevant activity. Ordinary planned work, annual notifications and urgent cases have different triggers.
- For an ordinary federal 10-working-day comparison, move backward from the work date without counting the work date itself.
- Check the receiving program’s calendar and submission method. A closed office may count as a federal working day but be unavailable for hand delivery.
Worked example
For a Monday, January 11, 2027 start, counting ten federal working days back gives Monday, December 28, 2026. If a separate ten-day clock excludes January 1 and December 25, that comparison gives Thursday, December 24.
Next step
Record the governing calendar, delivery cutoff and receipt alongside the planning date.