Which materials go in the linear, area and volume boxes?

Use linear feet for pipe material and square feet for other facility components. Cubic feet apply only to material off facility components when its length or area could not previously be measured. A container’s capacity is not a substitute for available original measurements.

How to approach it

  1. Keep each inspection entry in its original dimensional basis and identify which entries are RACM affected by this work.
  2. Sum like units across the applicable project. Compare each subtotal independently with 260 linear feet, 160 square feet or 35 eligible cubic feet.
  3. Equality meets the threshold. Never add feet to square feet or treat an unknown quantity as zero.

Worked example

Two affected ceiling areas of 85 and 75 square feet total 160 square feet and meet the area threshold. Another 40 linear feet on pipes stays in the pipe subtotal; the project is not “200 feet.”

Next step

Enter the inspection entries in the quantity worksheet.