When is an ordered demolition or emergency renovation different?

A qualifying ordered demolition requires a state or local government order based on structural unsoundness and danger of imminent collapse. Emergency renovation is a separate category for a sudden, unexpected event requiring immediate action for specified safety, equipment or financial reasons. Neither is a general waiver.

How to approach it

  1. For an ordered demolition, obtain the order and identify the issuing official, authority, order date and ordered start date.
  2. For an emergency renovation, record the event time, why an immediate response is necessary and the estimated RACM affected by the response.
  3. Contact the agency immediately. The qualifying federal branch calls for notice as early as possible before, but no later than the following working day. Confirm the local route and retain proof.

Worked example

A fire official acting for the city orders demolition because a wall is unsound and in danger of imminent collapse. The owner includes the order with the notice. A contractor’s request to meet a tenant deadline would not establish the same basis.

Next step

Give the authority the order or event facts instead of using the ordinary planner as a waiver.