SWPPP inspection report template
Fill in a same-day construction site inspection and print an unsigned report. For a blank form to take into the field, download EPA’s Word template under Official sources. Dewatering inspections and corrective-action logs are separate records.
Need the EPA form itself?
Use the blank EPA Word template if you work under its construction permit. For a site walk, the blank field sheet below records what you saw without inserting sample findings.
EPA · Download the blank Site Inspection Report Template (Word)Need a blank field sheet?
Print a clean copy before the site walk. It contains no sample findings and works offline when downloaded.
Worksheet
Your entries are calculated in this browser, not sent to CleanPermit. Print the result if you need a copy.
Your worksheet result
Worked example
A rain inspection reaches outlet 1, but a flooded bank blocks outlet 2. Keep the observed discharge and the inspection gap in separate sections.
See the result for the example inputs
- CONSTRUCTION STORMWATER INSPECTION • DRAFT / UNSIGNED
- Project / operator / location: Cedar Yard • North Lots LLC • east grading area
- Permit: Training permit EX-14 (illustrative)
- Inspection: 2026-04-14, 08:10–09:05 site local time • Rain event
- Schedule under permit: EX-14 §4B: 14 calendar days plus qualifying storms, east grading area.
- Inspection personnel: J. Lee, site inspector; training file Q-4
- Weather / trigger evidence: Gauge G1: 0.32 in between Apr 13 07:00 and Apr 14 07:00 local. Overcast at arrival.
- Phase / map route / controls checked: Rough grading; map rev 3: east slope, fuel pad, stabilized entrance, I-3 and outlet 1.
- Findings / noncompliance: I-3: fabric separated from frame; bypass to outlet 1 (photo E14-2, CA-04). Fuel pad: containment intact; no leaks observed at walk. Entrance: no track-out on road.
- Stabilization / exposed areas: East slope: grading paused Apr 8; blanket installed Apr 9. No bare patches or lifted edges observed.
- Outlets / receiving water: Outlet 1 flowing toward east ditch: tan water and fresh deposit at apron. Outlet 2 not observed.
- Access limits / follow-up: Outlet 2: flooded bank; no safe line of sight. Foreman to reassess from upper path at 12:00.
- Actions / attachments: CA-04: foreman assigned to contain bypass now and replace damaged control; due Apr 15 at 16:00 local under EX-14 §5. Photos E14-1 to E14-3.
- Before signature: attach the measurements, photos and action records you cited. Use the certification and signatory your permit requires. Under EPA CGP Part 4.7.1, complete the ordinary report within 24 hours after finishing the walk; the deadline to repair a control is a separate question.
- Authorized signatory: ____________________ Title: ____________________ Signature / date: ____________________
- File the completed, signed version with the site records. Printing this draft does not certify or submit it.
Guides for this worksheet
What belongs in a construction inspection report?
Someone who missed the walk should be able to retrace it: who inspected what, when and why, what they actually saw, and who is dealing with each finding. A checked box alone cannot distinguish a dry outlet from one nobody reached.
Open guide Guide / Field inspectionsHow do I record an outfall that is unsafe to reach?
Do not enter floodwater or an unstable bank to fill a box. Document the specific area you could not inspect and the reason; the limitation is not evidence that the outlet was dry, clear or compliant.
Open guide Guide / Field inspectionsHow should I describe sediment at an outlet?
Describe location, flow and appearance in words another inspector can verify. A visual observation can identify a problem but cannot establish a numeric turbidity value or prove the discharge meets a water-quality standard.
Open guide Guide / Field inspectionsWho can inspect the site and who can sign the report?
Field competence and signature authority are two different checks. Under the EPA CGP the operator must use a qualified inspector, while the report signature must meet Appendix G. A training certificate alone is not a delegation of signature authority.
Open guide Guide / Field inspectionsWhat should be recorded when grading pauses?
Track stabilization by disturbed area, not just by project. The key dates are when work stopped, when the expected pause became known, when protection began, and when it was installed. Work may continue elsewhere.
Open guide Guide / Field inspectionsDoes final stabilization automatically terminate coverage?
No. Field evidence supports the applicable termination condition; it does not itself end authorization. Determine whether completion, operator transfer or replacement coverage is the actual basis, then follow the issuing authority’s notice process.
Open guide