How to approach it
- For the EPA completion route, check each disturbed area against Part 2.2.14c and Part 8.2.1. Vegetation is evaluated relative to local undisturbed cover, not simply by whether seed was applied. Check nonvegetative cover, exceptions and remaining exposed areas.
- Capture the required representative before-and-after photos with dates, locations and descriptions. Check removal of materials, waste, equipment, temporary controls and pollutant sources against the permit’s exceptions for items that remain.
- Have the authorized operator file the required notice. Continue compliance until termination is effective, save the submission and effective-date evidence, and calculate record retention from the correct permit milestone.
Worked example
A parking lot is paved but its disturbed verge still has bare rills. The paving receipt does not establish final stabilization of the verge. Keep the project in inspection rotation while the gap is addressed.
Next step
Use the inspection report to record which mapped areas meet stabilization criteria and which still need work. Keep the supporting photos; the report is not a notice of termination.