How to approach it
- Name the outlet and receiving feature, whether water was flowing during the observation, and where you stood. Distinguish fresh deposits on pavement from suspended solids in moving water.
- Record color, visible solids, foam, sheen or odor as applicable, and visible conditions in the receiving feature attributable to the discharge. Note uncertainty about the source rather than assigning blame.
- Photograph the path and check upstream controls safely for bypass, overtopping or scour. Start the appropriate response and check separate sampling, dewatering or reporting duties; an image is not a meter reading.
Worked example
“At 10:20, tan flow leaving OF-1 formed a visible plume below the apron; deposited sand extended about 2 ft onto the apron. No meter reading taken.” Avoid “50 NTU” or “harmless silt” based on color.
Next step
Attach the images with time and map IDs, link any action taken, and schedule a check of the affected control.