What should be recorded when grading pauses?

Track stabilization by disturbed area, not just by project. The key dates are when work stopped, when the expected pause became known, when protection began, and when it was installed. Work may continue elsewhere.

How to approach it

  1. Mark the boundary on the current map. Record the last disturbance, anticipated restart and who confirmed the schedule. Check whether the area discharges to a sensitive water or has a shorter site-specific deadline.
  2. Under EPA Part 2.2.14 the trigger can arise when you know a temporary pause will last at least 14 days; do not wait until the fourteenth day to start. Initiation and completion are separate obligations with conditions and exceptions.
  3. Record cover installed, extent, date and any gaps. Revisit after weather to check for movement, bare soil or rills; document repairs and any change to the planned restart.

Worked example

On May 4 the grading lead parks work on the east bench until May 27. Record the bench boundary and that decision on May 4, not the date a delivery ticket arrives. Photograph the installed cover and inspect the downslope edge.

Next step

Record the condition and dates in the inspection report’s stabilization section; do not reduce inspections merely because seed was delivered.