How to approach it
- Start with the permit ID, inspector names and titles, date, times, construction phase and reason for the inspection. For event inspections, attach the actual measurements and source used.
- Use the current map to identify disturbed areas, controls, exits, discharge points and material storage areas. Describe both functioning controls and specific problems. Identify observed noncompliance; mark areas not observed and why.
- Cross-reference photo IDs, routine maintenance and corrective action entries. Use the applicable report deadline and authorized signature process. Under EPA Part 4.7.1, complete the report within 24 hours after finishing the inspection. Keep it accessible and retain it for at least three years after coverage expires or terminates (Parts 4.7.3–4). Part 4.6.3 addresses separate dewatering reports.
Worked example
“I-3 fabric separated at northwest corner; sediment fan on pavement beyond inlet; see photo 12 and CA-04” tells the foreman where to go. “Inlets checked” does not.
Next step
Use the inspection report template to draft today’s record. For a paper walk, download EPA’s blank Word template; check your issuer’s form and signature requirements before using either.