Disturbed acreage calculator
Measure distinct disturbance on your site, then check it against one acre with any additional ground in the same plan of development or sale.
Worksheet
Your entries are calculated in this browser, not sent to CleanPermit. Print the result if you need a copy.
Your worksheet result
Worked example
A grading plan shows 0.75 acre. A 1,210-square-yard access strip shares 242 square yards with it. The site footprint is 0.95 acre. Another 0.15 acre of utility work outside these outlines brings the same plan to 1.10 acres.
See the result for the example inputs
- Distinct footprint: 0.95 acres (41,382 square feet).
- In square feet: 32,670 + 10,890 − 2,178 counted twice.
- Full common-plan acreage entered: 0.95 acres on site + 0.15 acres of other distinct disturbance = 1.1 acres.
- The measured disturbance reaches the federal one-acre size threshold. Check discharge, operator and permit eligibility with the issuer; under the EPA CGP, prepare the SWPPP before submitting an NOI.
- Keep the dated outlines and units. One acre = 43,560 square feet; one square yard = 9 square feet. The size comparison uses unrounded inputs; it does not authorize work.
Guides for this worksheet
Do I need a SWPPP for less than one acre?
Possibly. For a lot under one acre, first ask how much land the whole common plan of development or sale will ultimately disturb. If that total reaches one acre, a construction stormwater discharge can require coverage even for a small lot. Where the EPA Construction General Permit (CGP) applies, an operator seeking coverage prepares a SWPPP before filing a Notice of Intent. If the entire plan is smaller, check for an agency designation and separate local requirements rather than assuming an exemption.
Open guide Guide / Construction coverageHow do you measure overlapping phases without counting land twice?
Measure the ground disturbed at least once over the plan’s life. This combined footprint differs from both the sum of all phase totals and the largest area exposed at one time. Keep those figures separate: temporary stabilization or a repeat excavation changes the work history, not the location of the ground.
Open guide Guide / Construction coverageDo staging yards and access roads count as disturbed land?
Look at what happens to the ground, not what the plan calls the space. Stripping a temporary equipment pad or grading a new haul road changes the footprint even if it is restored later. Using existing pavement without altering it presents a different acreage question; materials stored there can still affect runoff.
Open guide Guide / Construction coverageWhat evidence supports a small construction waiver?
A dry forecast or short grading schedule is not a waiver. First check whether the issuing authority offers one and which rules apply to the whole common plan. EPA Appendix C describes distinct low rainfall erosivity, approved TMDL and equivalent-analysis routes for small construction; the evidence for one does not establish another.
Open guide Guide / Construction coverageWhat changes when the footprint, operator or receiving water changes?
Keep three records in view: what changed in the field, what the current SWPPP shows and what the operator reported on its NOI. Updating one does not automatically update the others. Replacing an operator is different from correcting the same entity’s name.
Open guide