What changes when the footprint, operator or receiving water changes?

Keep three records in view: what changed in the field, what the current SWPPP shows and what the operator reported on its NOI. Updating one does not automatically update the others. Replacing an operator is different from correcting the same entity’s name.

How to approach it

  1. Make a dated before-and-after record: revised work limits, added acreage, changed flow route, affected controls and the entities controlling each area. Attach the marked-up map and planned effective date.
  2. For the same operator, check whether the SWPPP must change and whether an NOI field changed. EPA CGP Part 1.4.4 lists changes, including disturbed acreage and receiving-water changes, that trigger a 14-day review; affected work must wait as specified there.
  3. For a replacement operator under the EPA CGP, coordinate a new NOI ahead of transfer. The outgoing operator cannot rely on the transfer route for termination until it has transferred all areas under its control and the successor has obtained coverage. Keep both parties’ records.
  4. For a partial sale, mark transferred versus retained areas, who maintains shared controls and when control actually shifts. Check the permit’s update and termination procedures; do not close the entire site record simply because one lot changed hands.

Worked example

An operator adds a 0.25-acre laydown pad that drains to a second brook. Compare the revised acreage and receiving water to the NOI and update the site map and controls. If a new legal entity later takes over the whole job, start a separate operator handoff; renaming the old operator in the plan is not that handoff.

Next step

Set a handoff meeting around the effective records and unresolved shared controls, not just the closing date.