What evidence supports a small construction waiver?

A dry forecast or short grading schedule is not a waiver. First check whether the issuing authority offers one and which rules apply to the whole common plan. EPA Appendix C describes distinct low rainfall erosivity, approved TMDL and equivalent-analysis routes for small construction; the evidence for one does not establish another.

How to approach it

  1. Document the unique disturbed acreage and larger plan, operator, coordinates and expected construction period. For the federal small-construction size screen, distinguish at least one but less than five acres from a larger plan that will disturb five or more.
  2. For low erosivity, retain the official R-factor result, coordinates and dates from initial disturbance through final stabilization. EPA’s test is R less than 5, not a local rain total. Appendix C sets specific conditions for using interim nonvegetative stabilization as the end date.
  3. For the TMDL route, identify the receiving water, drainage area and EPA-established or approved analysis concluding that small-construction controls are unnecessary. For non-impaired waters, the equivalent-analysis route needs an actual pollutant allocation analysis, not simply a clean water listing.
  4. Keep the certification and its submission date. EPA requires submission before construction and approval for the TMDL and equivalent-analysis requests. If the schedule slips, check Appendix C before the original end date: a new calculation can change the next filing step.

Worked example

A crew expects to finish grading a 1.6-acre site on June 10, but its stabilization schedule extends through July 15. A calculator printout ending June 10 does not document that full exposure period. Use the supportable end date and retain the revised result; a worksheet or printout does not file a certification.

Next step

Take the full schedule, common-plan acreage and proposed evidence to the issuer; verify its process before relying on a waiver.