How to approach it
- Document the unique disturbed acreage and larger plan, operator, coordinates and expected construction period. For the federal small-construction size screen, distinguish at least one but less than five acres from a larger plan that will disturb five or more.
- For low erosivity, retain the official R-factor result, coordinates and dates from initial disturbance through final stabilization. EPA’s test is R less than 5, not a local rain total. Appendix C sets specific conditions for using interim nonvegetative stabilization as the end date.
- For the TMDL route, identify the receiving water, drainage area and EPA-established or approved analysis concluding that small-construction controls are unnecessary. For non-impaired waters, the equivalent-analysis route needs an actual pollutant allocation analysis, not simply a clean water listing.
- Keep the certification and its submission date. EPA requires submission before construction and approval for the TMDL and equivalent-analysis requests. If the schedule slips, check Appendix C before the original end date: a new calculation can change the next filing step.
Worked example
A crew expects to finish grading a 1.6-acre site on June 10, but its stabilization schedule extends through July 15. A calculator printout ending June 10 does not document that full exposure period. Use the supportable end date and retain the revised result; a worksheet or printout does not file a certification.
Next step
Take the full schedule, common-plan acreage and proposed evidence to the issuer; verify its process before relying on a waiver.