How to approach it
- Put each phase outline on a common scaled base. Include later access or grading beyond an earlier limit. Reconcile design revisions before measuring the overlap.
- Start with Phase A. For each later phase, add only its area outside everything already counted. For three or more phases, compare to the combined earlier outline, not each earlier phase independently.
- Retain the original outlines and a merged outline without internal boundaries. Label units and plan revision; keep full precision until the final display, especially near a reporting threshold.
- If the team also needs peak exposed area, use a separate timeline showing stabilization and reopening dates. A schedule by itself does not show how much of two phases occupies the same ground.
Worked example
A disturbs 0.80 acre. B disturbs 0.50 acre, including 0.30 inside A, so the combined outline is 1.00 acre. C disturbs 0.25 acre, of which 0.20 is already inside that combined outline. The project footprint becomes 1.05 acres, not 1.55, even if no two phases are open together.
Next step
Save both the merged footprint and the phase-by-phase exposure schedule so the next reviewer knows which number they are using.