Do staging yards and access roads count as disturbed land?

Look at what happens to the ground, not what the plan calls the space. Stripping a temporary equipment pad or grading a new haul road changes the footprint even if it is restored later. Using existing pavement without altering it presents a different acreage question; materials stored there can still affect runoff.

How to approach it

  1. Walk the logistics plan with the superintendent. Mark new entrances, trailer pads, utility trenches, stockpiles, borrow areas and disposal areas; include off-site locations in the review.
  2. For each area record the existing surface, proposed work, dimensions and any overlap with grading already measured. Show an unchanged paved lot separately from soil stripped along its shoulder.
  3. Separate acreage from discharge coverage. For a support yard, EPA CGP Part 1.2.1(c) asks whether it directly serves this work, is noncommercial, does not serve multiple unrelated sites, ends with the project and has the required stormwater controls.
  4. Give a reviewer both the acreage overlay and a list of support facilities with operators and drainage destinations. Do not assume a commercial supplier or an off-site yard shares the main site’s authorization.

Worked example

A temporary gravel entrance is 20 by 160 feet on previously vegetated ground. Its first 40 feet are inside the original grading outline. The addition is 20 × 120 = 2,400 square feet, not the full 3,200. An adjacent unchanged asphalt loading area stays on the pollution-source map, without counting its entire paved surface as new soil disturbance.

Next step

Add the measured new ground to the disturbance worksheet and show the paved loading area as a separate runoff-management question.