SPCC oil storage capacity inventory
Turn an equipment list into separate aboveground and completely buried totals. Flag unresolved containers before using the totals to screen a non-farm site.
Worksheet
Your entries are calculated in this browser, not sent to CleanPermit. Print the result if you need a copy.
Your worksheet result
Worked example
A 1,000 gal diesel tank plus six 55 gal oil drums gives 1,330 gal aboveground. Twelve 5 gal pails do not count. That is 10 gal over the ordinary aboveground cutoff, not proof that a plan is required.
See the result for the example inputs
- Counted shell capacity: 1,330 US gal aboveground; 0 US gal completely buried. Largest counted aboveground container: 1,000 US gal.
- Diesel tank: 1 × 1,000 = 1,000 US gal — counted aboveground.
- Oil drums: 6 × 55 = 330 US gal — counted aboveground.
- Pails: 12 × 5 = 60 US gal — excluded: each container holds less than 55 gal.
- No unresolved rows. Check for missing standby tanks, drums and oil-filled equipment.
- Ordinary non-farm capacity tests: aboveground exceeds 1,320 gal; completely buried does not exceed 42,000 gal on counted rows. Do not add the two totals. Check facility boundaries, discharge potential and exclusions separately; farms use a different screen.
Guides for this worksheet
Which containers belong in the oil inventory?
Start with every location that stores or uses oil, not just the tank farm. A 55 US gal drum counts at exactly 55; twenty 5 gal pails do not become a 100 gal container. Classify each item before adding its shell capacity.
Open guide Guide / Oil storage & SPCCUse shell capacity, not today’s oil level
Storage capacity is what the shell can hold, not the delivery limit, dipstick reading or amount left after a shift. A low-fill policy does not reduce the capacity entered in the inventory or the largest-tank containment check.
Open guide Guide / Oil storage & SPCCWhat to update when a tank changes
Treat a replacement, move, new foundation or piping change as a reason to revisit the site’s discharge potential. Under §112.5(a), a change in design, construction, operation or maintenance that materially affects that potential triggers a plan amendment; do not wait for the five-year review.
Open guide