How to approach it
- Compare before and after: total counted shells, largest tank, discharge direction, delivery point, containment and precipitation reserve. Mark new piping and valves on the diagram and update inspection or response procedures.
- For a material change, prepare the amendment within six months of the change and implement it as soon as possible, no later than six months after preparation. Track those as two separate dates. Maintain safe controls for current operations.
- Recheck plan eligibility and who must certify technical amendments under §§112.5(c) and 112.6. Keep the signed review and change record; the separate at-least-five-year plan review still applies.
Worked example
A yard replaces a 4,000 gal tank with a 6,000 gal tank beside its 3,000 gal tank. Total rises from 7,000 to 9,000 gal; with otherwise qualifying history it now screens Tier II instead of Tier I. Recalculate the berm for the 6,000 gal release and update the plan format.
Next step
Assign an owner to the amendment, field work and implementation date. Preserve the prior inventory so the change in tank size and plan path is auditable.