Florida construction NOI filing prep
Turn a start, expiration or takeover date into a filing target. Check the pollution prevention plan, receiving system and separate approvals.
Worksheet
Your entries are calculated in this browser, not sent to CleanPermit. Print the result if you need a copy.
Your worksheet result
Worked example
A new phase starts July 12 and drains to a county inlet. July 10 is the two-calendar-day filing target; an unfinished plan must be completed first.
See the result for the example inputs
- Planning target: submit the complete NOI and fee by 2027-07-10 (at least two calendar days before first soil disturbance on 2027-07-12). This is not a coverage start date. Under Part 2.7.1 coverage starts two calendar days after DEP determines the filing complete. Use the term on its acknowledgment.
- Hold the NOI: the form asks whether the SWPPP is developed and ready to implement. Finish the plan and identify its location before signing.
- Identify the operator and responsible signer. Gather coordinates, county, disturbance through completion, common-plan acreage, dates, receiving waters and dewatering details. Check the current fee and portal PIN or signed-mail instructions.
- Identify the receiving MS4 operator. Permit Part 2.6.4 says to send the NOI or acknowledgment within seven calendar days of receipt; DEP’s filing page asks for both. Send both and retain delivery evidence.
- Record the valid individual ERP number, issuer and phase. The NOI form offers an optional commencement notice for that existing ERP; it does not issue or amend an ERP.
- Ask the city or county about grading, connection and erosion-control approvals. Keep those responses separate from the state NOI receipt.
Guides for this worksheet
What goes into a Florida construction NOI packet?
Build the packet around the actual operator, the mapped work and a stormwater pollution prevention plan ready to implement. DEP’s NOI asks for the plan location; a draft plan is not ready to certify.
Open guide Guide / State filing desksWhat is the difference between a Florida CGP and an ERP?
The construction generic permit (CGP) addresses stormwater discharges during construction. Environmental Resource Permitting (ERP) addresses a different question, such as authorization for the proposed stormwater system or work affecting wetlands. One approval does not establish the other.
Open guide Guide / State filing desksWho gets the Florida construction notice when runoff enters a drain?
Trace the conveyance, not just the city boundary. A publicly operated ditch, inlet or pipe may be part of a municipal separate storm sewer system (MS4). The operator receiving runoff may be a county or district rather than the city.
Open guide