Florida construction NOI filing prep

Turn a start, expiration or takeover date into a filing target. Check the pollution prevention plan, receiving system and separate approvals.

Worksheet

Your entries are calculated in this browser, not sent to CleanPermit. Print the result if you need a copy.

Use the milestone that matches the filing above.

Worked example

A new phase starts July 12 and drains to a county inlet. July 10 is the two-calendar-day filing target; an unfinished plan must be completed first.

See the result for the example inputs
  1. Planning target: submit the complete NOI and fee by 2027-07-10 (at least two calendar days before first soil disturbance on 2027-07-12). This is not a coverage start date. Under Part 2.7.1 coverage starts two calendar days after DEP determines the filing complete. Use the term on its acknowledgment.
  2. Hold the NOI: the form asks whether the SWPPP is developed and ready to implement. Finish the plan and identify its location before signing.
  3. Identify the operator and responsible signer. Gather coordinates, county, disturbance through completion, common-plan acreage, dates, receiving waters and dewatering details. Check the current fee and portal PIN or signed-mail instructions.
  4. Identify the receiving MS4 operator. Permit Part 2.6.4 says to send the NOI or acknowledgment within seven calendar days of receipt; DEP’s filing page asks for both. Send both and retain delivery evidence.
  5. Record the valid individual ERP number, issuer and phase. The NOI form offers an optional commencement notice for that existing ERP; it does not issue or amend an ERP.
  6. Ask the city or county about grading, connection and erosion-control approvals. Keep those responses separate from the state NOI receipt.