How to approach it
- Draw a route for each outfall, from the site to the first conveyance and the receiving surface water. Use drainage plans and confirm ownership with public works or the relevant district.
- Check the DEP MS4 contacts and ask the receiving operator for its delivery address. Permit Part 2.6.4 says NOI or acknowledgment within seven calendar days of receipt; DEP’s filing page asks for both. Send both and keep the delivery receipt.
- Ask separately about local erosion inspections, grading approval and permission to connect or pump. Evaluate construction dewatering against its own CGP conditions; a copied NOI is not approval to pump.
Worked example
A site inside city limits drains through a county roadside ditch before reaching a creek. The superintendent confirms ditch ownership with the county, records its MS4 contact, and asks the city separately about a grading inspection.
Next step
Put the confirmed route, receiving contacts, copies sent and receipt dates in the site file. If ownership is unresolved, document who is checking it rather than guessing.