CleanPermit
Guide / State filing desks

What goes into a Florida construction NOI packet?

Build the packet around the actual operator, the mapped work and a stormwater pollution prevention plan ready to implement. DEP’s NOI asks for the plan location; a draft plan is not ready to certify.

How to approach it

  1. Collect the operator’s legal name, responsible authority, project contact, county, coordinates and water management district. Add the facility ID on renewal, and any relevant ERP number, issuer and phase.
  2. Record total disturbed acreage from start to finish, the common-plan context, construction dates, receiving waters, MS4 and dewatering details. Reconcile these with the SWPPP and map, and document the plan’s location.
  3. Use the current NOI and fee from DEP’s forms page. Prepare the portal PIN or signed-mail route. For a new project, submit a complete NOI and fee at least two calendar days before first disturbance. Save the acknowledgment and check its coverage term.

Worked example

For a July 12 clearing date the two-day planning target is July 10. If the SWPPP is still missing the discharge route on July 10, finish the plan and revisit scheduling rather than marking it ready or assuming a payment receipt authorizes work.

Next step

Keep submission and fee evidence, acknowledgment and posted copy. Check whether the receiving MS4 also needs copies.

Next on this task

Use the worksheet

All state filing desks resources →