What is the difference between a Florida CGP and an ERP?

The construction generic permit (CGP) addresses stormwater discharges during construction. Environmental Resource Permitting (ERP) addresses a different question, such as authorization for the proposed stormwater system or work affecting wetlands. One approval does not establish the other.

How to approach it

  1. For the CGP review, identify disturbance over the common plan, runoff routes, operator and proposed controls. Use the construction NOI and SWPPP, not the pond design approval, to document this track.
  2. For ERP, give the project location, plans, existing permit number and phase to the issuing DEP office, water management district or delegated local agency. Ask about the proposed footprint, system and any modification.
  3. Check city or county grading, connection and erosion-control requirements separately. Record each authority, number and conditions in its own file.

Worked example

A phase has an individual ERP for its pond. The CGP NOI allows an optional commencement notice for work already authorized by that individual ERP. Checking the box does not authorize an enlarged pond or establish CGP coverage by itself.

Next step

Before mobilization, compare the approved ERP phase limits with the disturbance map and confirm the CGP filing and local approvals independently.