Operator-role worksheet

Record who can change the plans and who can direct compliance work, one entity and phase at a time.

Worksheet

Your entries are calculated in this browser, not sent to CleanPermit. Print the result if you need a copy.

Use an organization or role rather than a personal name.
Cite a contract clause, site instruction or handoff record. If absent, identify what you need to request.

Worked example

A grading contractor cannot revise the design but can order a crew to repair sediment controls. Record the two answers separately rather than relying on its subcontractor title.

See the result for the example inputs
  1. Grading contractor — East pad · rough grading. Plan changes: No. Day-to-day compliance direction: Yes.
  2. Basis recorded: Earthwork agreement §4; superintendent directs the erosion-control crew.
  3. Plan control: name the entity that can actually approve a change and complete a separate row for it.
  4. Field control: record who this entity can dispatch to repair a failed control and in which area.
  5. Repeat for other entities and shared controls. Either type of control matters under EPA’s definition; the answers are evidence for review, not an assignment or release of permit responsibility.