How to approach it
- Identify the permitting authority first. The EPA CGP applies only where EPA issues it; a state-issued permit may use different forms, review periods and posting requirements.
- For the EPA CGP, prepare the SWPPP before submitting the NOI. Match operator, acreage, receiving waters and project limits across the plan and filing; resolve discrepancies rather than copying stale values.
- Save the signed filing, evidence of complete receipt, any agency correspondence, the tracking number and the effective date as distinct records. For an ordinary new EPA site, the usual review is 14 calendar days after EPA notifies the operator that it received a complete NOI, unless delayed or denied.
- Before scheduling earthwork, compare the intended start with the actual authorization record and applicable conditions. A local grading approval is a separate record, not a substitute for the stormwater coverage check.
Worked example
A SWPPP is signed Monday, the NOI is sent Tuesday and EPA requests a correction Friday. The team has a plan and a submission history, but Tuesday’s upload is not evidence the review period started. File the corrected NOI and look for EPA’s complete-receipt notice and any delay before recording an effective date.
Next step
Keep the plan, the filing history and the effective-coverage record together, with a different date and owner for each.