Tool / Industrial stormwater

Industrial stormwater permit issuer and sector finder

Identify a starting agency and look up a federal sector example. This is not a parcel-level jurisdiction check or a list of state permit requirements.

Worksheet

Your entries are calculated in this browser, not sent to CleanPermit. Print the result if you need a copy.

Use the facility location and operator, not the mailing address.
Selected federal examples; use “Other” for the full lookup.

Worked example

A Colorado federal operator runs a sawmill and a second industrial operation on the same parcel. Both the operator and the second activity affect the lookup.

See the result for the example inputs
  1. Start with the EPA regional stormwater program for Colorado. Verify the parcel and operator in the industrial (MSGP) column: https://www.epa.gov/npdes/authorization-status-epas-construction-and-industrial-stormwater-programs
  2. For EPA sites, check current permit status. Continuation after February 28, 2026 preserved prior coverage under the 2021 permit, not new coverage. No exposure certifications are separate. Check EPA’s instructions for your situation: https://www.epa.gov/npdes/administrative-continuance-epas-2021-msgp
  3. Screen federal Sector A1, SIC 2421. A shop assembling bought-in cabinets is not necessarily a sawmill.
  4. Record the primary activity and each additional industrial activity. Map them to outfalls and check each applicable sector; one facility can have several sets of requirements.