Crossing alternatives comparison
Compare two designs on the same crossing. See which footprints shrink, which grow and which measurements are still missing.
Worksheet
Your entries are calculated in this browser, not sent to CleanPermit. Print the result if you need a copy.
Your worksheet result
Worked example
A span reduces permanent wetland fill and reach disturbance, but its crane pad needs more temporary wetland access than a culvert.
See the result for the example inputs
- Embedded culvert → Clear span (same crossing and study limits):
- Permanent wetland footprint: 610 ft² → 140 ft² (470 ft² less).
- Temporary-only wetland footprint: 420 ft² → 720 ft² (300 ft² more).
- Affected stream reach: 85 linear ft → 20 linear ft (65 linear ft less).
- The measured changes trade off; no one design reduces every measured footprint.
- Before selecting a design, compare passage, flood capacity, restoration, access and cost against the same project purpose. Areas and lengths are not a permit score.
Guides for this worksheet
How can a design log show avoidance rather than just mitigation promises?
Show where an option moves work out of a resource, then show how the remaining work becomes smaller or less harmful. Compensation addresses residual effects; it does not replace that comparison.
Open guide Guide / Wetlands & crossingsWhat should I survey before proposing a replacement culvert?
Survey the crossing and the stream on both sides, not just the pipe diameter. Reviewers need to see the existing barrier, proposed bed profile and the temporary work needed to install the replacement.
Open guide