Tool / Wetlands & crossings

Aquatic impact quantity worksheet

Separate temporary-only and permanent footprints on one mapped feature. Reconcile shared ground without counting it twice.

Worksheet

Your entries are calculated in this browser, not sent to CleanPermit. Print the result if you need a copy.

Use one resource and one plan revision per worksheet.
Area inside the mapped resource, not the whole work site. Use 0 only if confirmed absent.
Include the permanent area even where temporary work occurs first.
Use 0 for verified separate footprints; leave blank if not measured.
Only use if fill of this thickness covers the entire permanent footprint. Not for excavation or variable slopes.

Worked example

A mat route covers 1,200 ft² of Wetland W-2. Of that, 150 ft² will also lie beneath the 400 ft² permanent approach.

See the result for the example inputs
  1. W-2 · approach revision B — gross temporary work: 1,200 ft² (0.027548209 acres); permanent: 400 ft² (0.0091827365 acres).
  2. Shared ground: 150 ft² (0.0034435262 acres). Temporary-only: 1,050 ft² (0.024104683 acres).
  3. Distinct disturbed footprint: 1,450 ft² (0.03328742 acres).
  4. Estimated permanent fill: 22.222222 yd³, using footprint × uniform thickness ÷ 27 after conversion to ft².
  5. Keep affected stream length in linear feet on a separate line. Disturbance area is not a finding of regulated loss.