How to approach it
- Label each wetland or reach on the plan. Clip work polygons to those boundaries; do not use the entire construction easement.
- For each resource, record permanent area, gross temporary area and shared area. Unique area = permanent + (gross temporary − shared). Divide ft² by 43,560 for acres.
- List reach length in linear feet rather than adding it to acreage. Tabulate material placed and removed separately in cubic yards. Keep dimensions and plan revision with the figures.
Worked example
In W-2, 1,200 ft² of mats overlap 150 ft² of a 400 ft² permanent approach. Temporary-only is 1,050 ft² and unique disturbance is 1,450 ft², not 1,600 ft².
Next step
Mark the intersection on the plan and check the worksheet against the district’s requested impact categories.