How to approach it
- Use pre- and post-grading contours to sketch flow arrows. Give each site exit a distinct ID. Check low points, overflow paths and temporary diversions; one site can drain in opposite directions.
- At each pipe or ditch, record the inlet and outlet IDs and match them to the drainage plan or the storm sewer owner’s asset records. Observe only from a safe, authorized surface location; never enter a structure to complete the trace.
- Record the last supported link and the source for it. Mark missing connections as unknown. Ask the system owner for the outfall sheet rather than drawing a straight line to the closest waterbody.
- Once the route is supported, check receiving-water names, impairments and designations against official records. Keep the map edition and verification date; a mapped route is not a determination of federal jurisdiction.
Worked example
The nearest creek lies west of a parking lot. The city asset map shows inlet I-4 flows east through pipe P-6 to outfall O-12 at a different brook. Label I-4 and O-12 separately and save the map reference. If the sheet ends at P-6, record “receiving water unknown” until the next link is found.
Next step
Complete a drainage worksheet for each site exit and send the unresolved asset IDs to the storm sewer owner.