CleanPermit
Guide / State filing desks

Texas small site notice or Notice of Intent?

Texas separates the site notice posted in the field from the Notice of Intent (NOI) filed with TCEQ. The ordinary small-site notice route does not require an NOI, but site size alone does not select the route.

How to approach it

  1. Mark all proposed soil disturbance on a plan. Check plats, roads, utilities and other phases for a common plan of development or sale; compare disturbance, not parcel size.
  2. For the ordinary small-site route (at least one but less than five disturbed acres, including the common plan), review eligibility and prepare and implement the SWP3. Follow TCEQ’s posting instructions and send the signed notice to any receiving MS4 at least two days before construction.
  3. For five or more disturbed acres under the project or common plan, review primary versus secondary operational control. A primary operator’s large-site route includes an NOI and a posted notice; a secondary operator uses its own notice under the permit’s conditions.

Worked example

A builder disturbs 0.8 acre inside a subdivision with six acres of planned disturbance. Before choosing a form, compare the plat to the disturbance limits and identify who controls the work. Do not treat the lot as an isolated small site.

Next step

Confirm eligibility and any special erosion or waiver provisions in TXR150000 before selecting the form. Use the current notice for the route: 20963 for ordinary small sites, 20961 for large-site primary operators or 20962 for secondary operators. Keep the signed notice and MS4 delivery record with the SWP3.

Next on this task

Use the worksheet

All state filing desks resources →