How to approach it
- Map the sold area, unfinished disturbance and shared controls. List who directs work and maintains each inlet, fence and basin before and after the handoff.
- For a large-site primary operator transfer, read Part II.F.4 before scheduling closing: the new operator’s NOI is due at least ten days before transfer, and the original operator’s NOT within the ten days prior to its responsibility ending. Check conditions and copies to receiving MS4s; notice-only operators have a different notice replacement process.
- For an individual residential home, check the Part I definition of final stabilization. Document final stabilization or the specified temporary stabilization and homeowner notification route in the builder’s SWP3; use the state homeowner notice to identify remaining work.
Worked example
A developer sells two unfinished pads but still runs the shared basin on eight unsold lots. Map the pads and basin separately, identify who services their controls, and check the operator-change steps for the pads. The sale is not a reason to close coverage for the entire subdivision.
Next step
Record possession and control dates, incoming operator documentation, stabilization evidence and notices. Resolve uncertain boundaries with TCEQ before removing controls.