Turn a rainfall depth into a freeboard reserve

Freeboard is capacity kept available for precipitation, not an arbitrary strip of unused wall. Storm depth in inches divided by 12, multiplied by contributing square feet, gives cubic feet of water. Multiply by about 7.48052 for US gallons.

How to approach it

  1. Document an appropriate local design storm and its source. EPA describes a 25-year, 24-hour event as appropriate for most facilities, not a mandatory nationwide value. For a site covered by NOAA’s Precipitation Frequency Data Server, select its location and read the precipitation depth at the selected duration and recurrence interval, not an intensity in inches per hour. Save the table with the site coordinates and date.
  2. Trace the catchment. Include roofs or adjoining pavement draining inward, without double-counting overlapping footprints. A roof does not justify a zero rain reserve if wind-driven rain or run-on still enters.
  3. Compare the calculated gallons with the space remaining after the release and displacement. Maintain drainage controls and inspection records; do not credit an open drain or assume pumping will occur during the storm.

Worked example

A 240 ft² basin also receives runoff from 60 ft² of adjacent paving. Four inches over 300 ft² is 100 ft³, or about 748 gal. Counting only the basin would understate the reserve by about 150 gal.

Next step

Put the storm source, catchment sketch and drainage assumptions alongside the calculation so the next inspection can verify them.