Subtract what occupies space inside a berm

Length × width × wall height is gross space. Water and solids already inside share that space with a release. Count the volume of surviving equipment below the overflow elevation, not the nameplate capacity of every tank in the enclosure.

How to approach it

  1. Choose a failure scenario and the lowest escape elevation. Measure inside dimensions from the actual floor; for sloping ground or unequal walls, obtain a survey or elevation-volume calculation instead of treating the area as a full box.
  2. For intact tanks, foundations, supports and pipes, determine the volume physically below the overflow level. Do not remove overlapping volumes twice, and document your assumption about the failed tank. Recheck other release scenarios if the controlling displacement could change.
  3. Convert cubic feet to US gallons (1 ft³ ≈ 7.48052 gal), subtract displaced gallons and measured standing liquid, then reserve precipitation. Compare what remains with the entire shell of the largest tank served.

Worked example

An intact vertical tank 4 ft in diameter sits on an 8 × 4 ft pad. At a 2 ft overflow height, a 0.5 ft solid pad displaces 16 ft³ and the tank above it displaces π × 2² × 1.5 ≈ 18.85 ft³. Enter 34.85 ft³ (about 261 gal) for these obstructions, not the tank’s shell gallons. Do not count the overlapping pad height again.

Next step

Retain the sketch with object dimensions, elevations and the failed-tank assumption. Revisit the calculation when equipment is added inside the berm.