How to approach it
- Describe where fill, bedding or rock would be placed, how much and for how long. Identify the federal license or permit under discussion rather than assuming every project has one.
- Ask which certifying authority serves the discharge location: generally the state or authorized Tribe, or EPA where neither has authority. Check whether an existing certification covers the proposed federal permit and on what terms.
- Track the certification decision or documented waiver separately from the federal action. Carry relevant conditions into the plans; do not treat filing a request as a waiver.
Worked example
A bridge plan adds rock at an abutment. The 404 discussion tracks placement and footprint; the 401 discussion might also address how turbidity from that work will be controlled.
Next step
Give both offices the same drawing revision and ask how they want the two records cross-referenced.