How to approach it
- Match project number, location, permittee, quantities, footprint and plan revision to the planned work. Mark any changed feature, access route or construction method.
- Make a condition register: note the action, responsible person, evidence and due date for work windows, notices, inspections, restoration, monitoring and closeout where specified.
- Separate completion or expiration dates from reporting deadlines. If timing slips, the NWP changes, or the design differs, send the district the dated record and revised schedule before relying on the letter. Do not assume an extension or transition period applies.
Worked example
A verification references a 24 ft approach, but the bid set widens it to 30 ft and moves the mat route. Highlight both changes and ask for written direction before mobilizing.
Next step
Keep the agency response, referenced drawing set and condition register together in the field copy.