How do I close a California construction stormwater record?

Use a Notice of Termination (NOT) for the correct active WDID. A last day of grading, sale or submitted request does not by itself end the statewide permit obligations.

How to approach it

  1. Check the applicable reason in the 2022 NOT guide: for completed or suspended construction, verify final stabilization. For a transfer or other basis, collect evidence specific to that reason; coverage does not simply transfer to a new owner.
  2. Open the active record and select File NOT. For a completed traditional project, assemble final map, QSP final inspection, photographs and applicable long-term maintenance and final post-construction plans. Check the permit for reason-specific attachments.
  3. Have the LRP or authorized DAR certify in SMARTS. Track Regional Water Board questions and approval. The discharger remains responsible for compliance and accrued annual fees until approval.

Worked example

A site is paved, but the final QSP inspection shows an unstabilized slope. Mark the slope on the map, document the corrective work and take follow-up photos. Do not use the paving invoice as proof that the whole site is stabilized.

Next step

Keep the submitted packet, board correspondence and approval showing the effective termination date. Confirm the status of the WDID before marking the record closed.