What should a construction stormwater site map show?

A useful site map lets a new inspector locate disturbed ground, follow runoff and find the control that protects each discharge point. An architectural plot plan alone rarely answers those questions. EPA CGP Part 7.2.4 provides a detailed list; use the applicable permit’s list as the final check.

How to approach it

  1. Start with a legible base showing property limits, construction limits and phase boundaries as different lines. Add a scale, north arrow, revision date, preconstruction cover, slopes before and after grading, stockpiles, paved exits and support areas.
  2. Show drainage arrows, water crossings, discharge points and any storm sewer connections. Use an inset for downstream waters: EPA Part 7.2.4 calls for receiving waters on site and within one mile downstream of discharge points, including applicable impairment and tier designations.
  3. Plot controls, buffers and pollutant sources using IDs shared with the SWPPP and inspection forms. Include washout and waste areas where applicable. Use layers or a second sheet if the labels obscure the field locations.
  4. Walk a route with the printed drawing. Can a substitute inspector find control C-3 and tell which discharge it protects? Record the verification date and revise the map and plan when field changes make them inaccurate.

Worked example

The grading sheet labels one basin, but a field walk finds two inlets and an overflow swale. On the site sheet, label I-1, I-2 and overflow D-2; use a downstream inset for the pipe connection. If D-2’s destination is unverified, draw that segment dashed and assign someone to confirm it.

Next step

Give the field team the revised map and record who will verify the dashed connection.