Is this routine maintenance or a corrective action?

Decide from the condition, not how quickly the crew can fix it. Minor upkeep that keeps a functioning control effective differs from a missing control, major repair, replacement or another permit-defined trigger.

How to approach it

  1. Record the damage, original design, evidence of discharge, and previous fixes to the same control at that location. Check the exact maintenance and corrective-action clauses.
  2. EPA Parts 2.1.4c and 5.1.1 address three or more of the same fixes at the same control and location. EPA’s inspection template counts the current occurrence. Record the repair history and use Part 5 corrective action unless you document in the inspection report why this specific recurrence should still be routine maintenance.
  3. For corrective action, take the required immediate steps, assign an owner and deadline, and record completion, verification and whether the SWPPP must change. Under EPA Part 5.4 the discovery and completion entries each have their own 24-hour documentation window; that is not the repair deadline.

Worked example

Removing ordinary sediment from an intact inlet filter can be upkeep. Discovering that a required inlet control was never installed is an EPA Part 5.1 trigger even if a crew can install it that afternoon.

Next step

Link the decision to the inspection and use the corrective-action register for findings that meet the trigger.